You are here: Part II
A Symphony of Cuts –Reform instead of rite
Saving options on a concrete, anonymized project example in figures
Reform instead of rite
Overture: Diagnosis of the standstill
Architecture is frozen music, the Romantics used to say. If so, we are now witnessing global climate change in building culture: the work is not merely thawing; it is turning to sludge. After Part I, “A Paper Trail into the Earth” dissected the moral and legal paralysis caused by the question of guilt, the sonic result now becomes apparent: what was once built in time—with tempo, clarity and compositional rigour—dissolves into legal clauses, seeps into checking notes and drowns in a deluge of regulations. Requirements settle over the design like an unceasing, dissonant noise until only a residual murmur remains of the melody.
Public construction is thus no longer the virtuoso interplay of a string quartet of architects, engineers and authorities working on a shared score, in precise correspondence and with mutual responsibility. It resembles a stage full of soloists: each sounds their own entry, plays their own variation claim and covers their own liability, while the total work of art is lost in the administrative din. Restoring cost, time and quality to a harmonious triad requires more than technical corrections. This diagnosis is no swan song, but the prerequisite for reform: it calls for a recomposition of decision-making power and responsibility.
This standstill is the result of decades of layering, as though ever more voices had joined the ensemble: increasingly strict rules of play in procurement law, a growing score of technical standards and a tightly scheduled cycle of rehearsals and acceptance inspections conducted by supervisory bodies. The historical result has been an ever finer division of tasks within construction and planning. The AHO—the German committee of engineering and architectural associations and chambers concerned with the fee schedule—dates key stages in the differentiation of service disciplines to the 1970s.1
Historically, this conjunction is no accident. It was a response to a convergence of pressures: as early as 1971, a process of legal harmonisation began for public-works procurement in the European Economic Community (EEC)2—an instrument for realising the internal-market freedoms of the Treaty of Rome and opening a public-procurement market that had operated as a non-tariff trade barrier. In Germany, successive waves of formalisation followed in procurement law; alongside them, the fee schedule for architects and engineers (HOAI) was composed in 1976.3 By this point at the latest, every design had become a case file and every decision a file note of the kind familiar today. The oil-price crisis of 1973 intensified the pressure: the response to the price shock was not courage to decide, but reflexive control—in the superstitious belief that volatility forgives fewer mistakes and can be tamed only by more documentary proof and tighter direction.4
The chain is as logical as it is fatal: opening up markets creates a greater documentation burden; that burden generates more demands for evidence and scrutiny; more scrutiny creates more roles—and, in the end, less courage to decide precisely where something has to be built.
In such an ecosystem, new roles are almost inevitably created to mitigate decision-making risks. Responsibilities are shared and ambiguities externalized – Every step is rational locally, but globally crippling and expensive. While the architect has long been considered the last generalist, a conductor who has had to hear culture, sociology, structure and financing at the same time, today’s overview increasingly disintegrates into niche specialties. The emergence of such synthetic professions as the AHO project controller, the BIM manager, the safety and health coordinator (SiGeKo) and DGNB consultants for sustainability certification only fill the resulting vacua.5
The practice of large public projects shows that this is no mere theory: the administrative layer cannot keep pace with the building site and actively works against its rhythm. Bureaucracy’s own cycle of checks often generates precisely the additional costs it believes it is preventing. On one public construction project, after years of interim payments and audit notes, an invoice for late-payment interest eventually landed on my desk—not for one disputed payment or an isolated exception, but systematically for every interim invoice the contractor had submitted over the course of the project. The point is less the legal basis of the claim than the stark possibility of reducing a construction project to an interest-bearing instrument through administrative delay.6,7 Speeding up payments without structural reform often treats only the symptom: the cost driver lies in the checking process itself. Calls for acceleration can merely fuel further cost increases when redundant checks and loops of follow-up queries remain intact. Yet looking back must not become an exercise in historical idealisation: many standards resulted from necessary developments in the law and higher levels of protection. The problem begins where quality is no longer built, but principally administered.8
On another publicly funded construction project—the renovation of a Berlin cultural complex—the original design practice had to be replaced because its planning was inadequate9; work on site threatened to grind to a halt. There was no time for a regular procurement procedure taking about a year (!), so a new architectural practice was directly commissioned to complete the remaining services. The procurement-law assessment of this decision is left without comment here. The new architect reported substantial deficiencies in the inherited detailed design—yet the real fault lay in the process: formal appointment dragged on for months, procurement-law problems had to be wished away after the fact, and the proposal was revised, renegotiated and supplemented with ever more documentary evidence countless times. Work began because the commission had been granted in principle, but the contract lagged behind. There was consequently no agreement on its value. For almost a year, the practice had to finance several employees assigned specifically to the project without being able to rely on payment.
As the state takes on ever greater weight as a client in the construction sector, driving its share of the economy to disproportionately large, seemingly socialist levels, this example illustrates more than why small and medium-sized businesses—the backbone of the German economy—are shrinking: young architects and business founders simply cannot afford such a long period of advance financing. It also shows how the state apparatus is ultimately reduced to generating payment reminders and fees. The diagnosis is simple: a system intended to prevent standstill produces it through administration—and then pays for it in late-payment interest and mistrust.10
In this system, courage and responsibility are regarded as risk and risk aversion and formalities as security. Therefore, hesitation seems to have become a rationally learned survival strategy in public structures. A reform has to start here: we do not need more efficient management of the standstill, but decision-making power with clear responsibility. Not “to build faster” is the imperative of the hour, because structural and planning processes require a minimum time, but “to decide more quickly and be more clearly responsible”. The goal must be a politically supported building of competence with the client, which allows pragmatic weighing again.11
Precisely because building law is largely a matter for Germany’s federal states, Berlin can make a decisive difference here. The following five approaches to reform are illustrated using an anonymised example: a completed new public-sector building in Berlin with a gross project volume of EUR 60 million (cost groups 200–700).
One final observation is in order: we calculate, inspect and negotiate using a vocabulary that is far from exclusively German and belongs to the same cultural sphere as music: budget, netto, brutto, in toto. Yet while we have retained the terms of calculation, we have lost our feeling for tempo. A state that does nothing but administer forgets how to conduct. The reforms that follow therefore aim at more than administering standstill more efficiently. They set the tempo for renewed action, divided according to the time horizons of their effects: Allegro, Adagio and Largo.

— Annex: Reform scenario of the reference project Technical development of the time horizons Allegro, Adagio and Largo. —
The first movement of many concertos is fast, incisive and thematically clear. Allegro also means determined and forward-driving. The reforms that follow aim at just that: cutting out, leaving out, cutting back—with resolve, to accelerate the political, administrative and constructional tempo.
Radical streamlining of cash flows
Finding: Invoice checking through successive bodies creates a break in rhythm between actual construction work and its administrative recognition: site supervision, project control, client and funding body read the same document four times. This endangers the liquidity of medium-sized construction companies, intensifies conflict and can, in extreme cases, halt construction or lead to contractors’ insolvency. Where the technical reviewers on the site-supervision side are unsure, the checking process expands not merely through more stages, but through more loops of queries and requests for further documentation—time that no longer produces any gain in quality.12
Proposal for reform: Establish no more than one checking body in the construction process: site supervision. In support, the medium-term task is to strengthen specialist site supervisors’ competence as stewards of a public client’s assets. Mandatory training in checking invoices and variation claims could be a prerequisite for admission to professional chambers and authorisation to work on site. Entry in the Berlin Chamber of Architects’ register currently requires evidence of attendance at seventy 45-minute units of further training in specified fields; no final examination or demonstration of competence is required13—which can cost clients unnecessary money. In the longer term, these core competencies must be embedded in degree courses. The aim is to shift the emphasis towards greater competence in checking; the “check of the check”, the so-called verification by project control, would then become unnecessary.
Cost effect: If, irrespective of the VOB requirement of 21 calendar days14, the checking process for a construction company’s interim invoice currently takes an average of 20–40 days before payment, it could be shortened by 10–20 days. Over the construction period, this means fewer interruptions to work, fewer escalations and fewer claims arising from extended construction time. Shorter checking cycles would yield a cumulative time saving of one to two months. For a construction volume of EUR 50 million, plus EUR 10 million in ancillary construction costs, experience puts time-dependent costs—site overheads, equipment kept on standby, construction management, site security during waiting periods and claims for additional payment due to extended construction time—at around 0.2 per cent of a construction company’s total contract value per calendar week. At EUR 50 million, a saving of one to two months corresponds to EUR 0.4–0.8 million. That would pay for two or three additional ambulances.15
Concentration instead of externalisation (audit responsibility)
Finding: Interfaces proliferate where decisions are lacking. Every ambiguity is covered by external expert reports, second opinions and additional rounds of coordination and checking. Eliminating successive duplicate checks by external experts, project controllers and authorities frees substantial capacity without compromising safety.
Proposal for reform: The principle of undivided responsibility for technical checks. In defined fields—bids, variation claims, invoices, structural calculations and fire safety—a suitably qualified professional replaces subsequent duplicate checks; responsibility and liability are clearly assigned. Decision-making power is concentrated rather than dispersed through cascades of checks. Decision-making power is concentrated internally rather than externalised.16
Cost effect: Reduction of redundant expert reports, coordination and control hours and their assignments. approx. € 1.0 million.17 Depending on the income, these are up to 20 gross annual salaries, 25 middle class cars or 10 rehabilitated schools.
Adjustment of the funding and tax framework
Finding: Rigid reporting deadlines in grant administration—monthly reports, quarterly reports and interim statements on the use of funds—generate coordination work, consume time and tie up resources.
Proposal for reform: Transition to a support practice that accepts multi-annual realities.
Cost effect: Faster processing of invoices and variation claims (see the first reform proposal).
Adagio literally means “at ease”, “comfortably”. Here belong reforms that consolidate responsibilities, bring procedures together and require a longer lead time to implement:
Liability for technical planning and verification tests
Finding: Most construction disputes begin not in court, but in everyday practice: changes, delays and obstructions, deviations, the consequences of missed deadlines and questions of payment become legal issues because instructions and money are linked. Public procurement is designed to ensure traceability and a defensible documentary record.18 Anyone required to examine contract awards, suitability, bid evaluation, review procedures and file notes for legal compliance often routinely seeks legal advice—less out of a taste for dispute than out of fear of the consequences of procedural errors. The VOB is not the problem. It provides deadlines, checking procedures and mechanisms for resolving conflicts—yet public construction projects often remain permanently preoccupied with covering themselves. The reason lies in the surrounding system: procurement, budgetary and audit regimes overlay contract law and create perverse incentives. Wrong decisions and procedural errors can be traced to individuals; construction delays caused by protracted procedures intended to avoid wrong decisions are rarely penalised, because responsibility is dispersed. The result: delay is often “cheap” for the administration; a decision is “expensive”. A “safe file” thus matters more than swift progress on site; technical questions are channelled into checking procedures, rounds of queries and legal safeguards. Lawyers spend less time settling disputes than continually shielding against risk. If the VOB already provides mechanisms for resolving conflicts, the most effective reform lies not in inventing new instruments, but in detoxifying the existing ones.
Proposal for reform: Reconnect responsibility and costs. Legal advice must not remain a vague line of ancillary costs, topped up through the next supplementary submission. Each project should have a fixed number of permitted legal consultations; anything beyond that should require a reasoned escalation, a formal request and approval at the decision-making level. The aim is not “less law”, but less retreat into legal procedure.
Cost effect: Any credible estimate of the financial effect must be given as a range, since it depends heavily on whether legal clarification is needed and how much. For a project volume of EUR 60 million, the benefit typically lies in the mid-six-figure range, roughly EUR 0.2–0.8 million. That would pay for two large children’s playgrounds in a medium-sized German city, or a spacious owner-occupied flat in a major German city.
Simplified building types and streamlining of standards
Finding: Berlin should advocate “Building Type E” at federal level and pilot it in state law. The idea is that technically straightforward buildings—housing up to a certain height, for instance, or schools with regular floor plans—would be subject to a reduced set of standards. According to the Federal Ministry of Construction, fewer exceptional technical cases and more standard solutions could reduce construction costs by around ten per cent, translating into lower rents and purchase prices per square metre.
Proposal for reform: Strip back Berlin’s building regulations systematically. State-specific regulations that go beyond federal requirements—such as special energy standards, parking requirements or obligations to provide greenery—must be assessed for their actual added value. At present, environmental requirements for solar panels on public buildings and nature-conservation requirements for trees appear ideologically driven. A review of the existing body of standards could identify provisions to remove or alternative ways of complying, such as solutions tailored to users rather than rigid DIN requirements. Alternatively, every new standard must be accompanied by the abolition of an existing one.
Cost effect: A simpler building scheme would, on a conservative estimate, reduce costs by five to ten per cent—around EUR 3–6 million in the school example—principally through reduced planning work. Crucially, this saving must not be rationalised away in full. It is wiser to reinvest part of it in material quality and design. The resulting building costs less overall, but its more robust floors and better junction details give it a longer service life: lower costs and higher quality at the same time.
A particularly slow, sustained pace with a calm, dignified character. Trust instead of mistrust, responsibility instead of protection, building culture instead of process culture:
Change the procurement and contract culture
Finding: The fundamental question concerns economic incentives: how is public-sector construction organised? The prevalent approach to contract awards—price before quality—combines with rigid works contracts to foster a destructive “economy of variation claims”. Bidders price their bids tightly, knowing that every design change and uncertainty—ground conditions, weather, price rises—will later be negotiated as a variation claim. When responsibility is fragmented, each participant optimises their own segment; the project’s objective disappears from view.
Reform proposal A (life cycle): Robustness and lower subsequent costs must pay. Contract awards should be based not primarily on the initial investment up to completion, but on robust whole-life assumptions: service life, the building’s life cycle and maintenance requirements. The horizon must therefore extend beyond the term of office of a public-sector client or the public body whose needs the building serves.
Reform proposal B (contracting and project-delivery model): Berlin should deliberately test new approaches, including pilot projects with alliance contracts or integrated project delivery (IPD; German abbreviation IPA)19, alongside design-and-build procurement. Designers and contractors are brought together early and jointly committed to a target-cost budget; bonus-and-penalty provisions—sharing savings and clearly allocating risks—reward project success rather than variation claims or rising eligible construction costs, as happens now! At the same time, quality must gain appreciably in contract-award evaluations relative to price alone. For the state of Berlin as client—for example, in its school-building programme—the publicly accessible contractual documents instead suggest a conventional framework-contract and allocation-of-roles model; an alliance contract or IPD is certainly not envisaged as the guiding model there.
Cost effect: This transformation of construction and contracting culture requires time to develop expertise and adapt the legal framework. Yet the potential is immense: when all participants pursue a common goal, massive cost overruns—doubling, in an extreme case, from EUR 30 million to EUR 60 million—can be effectively prevented. Realistic savings of ten to fifteen per cent, around EUR 6–9 million on the reference project, would come from eliminating risk premiums, completing work sooner and reducing conflict. Such alliance models nevertheless require sound preparation through trust-building and external facilitation, to avoid sliding back into old patterns of blame. Building design shows how fragmented responsibility itself inflates planning costs: constant redesign and documentation requirements generate their own dynamic of variation claims.20
Clear protection objectives and balancing instead of rigid addition of standards
Proposal for reform: Berlin should create genuine scope for discretion in its building regulations and administrative practice. Prioritising safety objectives according to risk permits highly economical solutions within the existing legal framework: instead of demanding the absolute “best solution” for every corridor and room, priorities could be set. Safe evacuation and ground-floor accessibility, for instance, could be given very high weight, while a ventilation standard is applied more flexibly, provided indoor air quality is maintained. Safeguards for innovation and the exercise of judgement could be established. If architecture is to become more musical again, the conductor—the authority—needs assurance that a misjudgement made in pursuit of innovation will not end a career.
Such exceptions are already legally possible under § 67 BauO Bln (exemptions and departures). Yet they are rarely used because public decision-makers fear being held personally liable. Political backing is therefore needed to establish the exercise of judgement as intended practice, so that the overall level of protection can be achieved more efficiently.
Finding: Many costs arise because requirements are added cumulatively. The requirements for energy efficiency, accessibility, fire protection, room air quality and acoustics apply, which currently have to be fulfilled simultaneously maximum. This inevitably leads to highly complex and expensive special solutions.
Cost effect: In the anonymised example, some access hatches, ventilation and air-conditioning systems, or safety systems could be dispensed with. Estimated savings are five to eight per cent of the total project, roughly EUR 3–5 million—partly as a reduction in costs, partly as a reserve for improvements in quality elsewhere.
The current system is not the product of collective irrationality, but the result of overlapping, fundamentally legitimate objectives: safety, equal treatment, corruption prevention and comprehensive invoice checking have piled up into a wall over decades. The problem lies in the perverse incentives this produces: individual risk aversion is rewarded within the apparatus, while courageous, pragmatic judgement is punished. A non-decision has no consequences for the individual decision-maker—yet for the project as a whole, it is the most expensive conceivable outcome.
This is precisely the core of a real reduction in bureaucracy: it’s not about “less state”, but about better incentives, the return to individual responsibility and a standard of proof that matches the actual risk. If this realignment of responsibility is seen as a guiding principle, the five reform levers change from a mere set of measures to a necessary system diagnosis.
Tax rules compound the problem: while input VAT refunds usually arrive promptly,21 accrual-based VAT requires companies to finance VAT liabilities long before payment actually arrives—an often underestimated drain on liquidity that needlessly jeopardises their financial stability.
Encore
Taken together, these reforms aim to turn procedural complexity into efficient solutions. A conservative estimate puts potential savings at eight to twelve per cent: around EUR 4.8–7.2 million on the EUR 60 million reference project. Simply adding these potential savings together would, however, oversimplify the realities of construction. There must be a flow of reinvestment from paper into walls, so that a new building is optimised not merely for expenditure, but also for the robustness and longevity of materials, precision of detail and well-executed junctions beyond completion.
The way there is tripartite, and it remains quantifiable.
- Immediately (Allegro): Streamline cascades of checks and eliminate duplicate checking. Savings: EUR 1.6–2.2 million, around 2.7–3.7 per cent. This takes effect immediately and sends a clear signal to small and medium-sized businesses.
- Medium term (Adagio): Streamlining standards and piloting “Building Type E” create room for simpler construction without compromising quality. Savings: EUR 3–6 million, five to ten per cent.
- Long term (Largo): A change of mentality, supported by suitable contracting and project-delivery models—alliancing and integrated project delivery—and sound contract-award criteria, can structurally prevent cost overruns. Tax-law reforms provide a further lever. The potential here is EUR 6–9 million, ten to fifteen per cent.
What does this amount to? Ten projects of this scale represent a total volume of EUR 600 million across roughly five biennial budget cycles. A conservative range of eight to twelve per cent corresponds to around EUR 48–72 million—funds that could either genuinely be saved or invested in new projects. That would make eleven major projects: one more school, one more theatre modernisation, one more block of flats!
So far, we have spoken of levers, percentages and sums of money. That is necessary. But it is not enough. Even the best score remains paper if no one in the orchestra pit has the courage to give the cue. In many places, the virtuoso interplay of the string quartet of clients, architects and authorities mentioned at the outset has been replaced by a web of prompters and inspectors who talk over the musicians without respite, until playing gives way to covering oneself. A reform that seeks to overcome this standstill cannot stop at technical details. It must make responsibility clearly assigned again. Visible. Capable of being shouldered.
The deeper question is cultural rather than technical: who decides when it really matters? The closing passage therefore turns to the broad, sustained movement without which every building remains soulless: the courage to decide. It looks back at how responsibility was once visible, how it fragments today, and what culture of decision-making we need again, so that architecture may become frozen music—so that architecture may sound again.
- On the differentiation of performance disciplines in the 1970s, see: AHO – Committee of the Associations and Chambers of Engineers and Architects concerned with the fee schedule: Issue 9. Project management in the construction and real estate industry – standards for services and remuneration. 5th, fully revised edition. Available online at: https://www.aho.de/publication/heft-9/ (last access: 09.01.2026). ↩︎
- As early as 1971, the EEC establishes a framework for coordinating procurement procedures for public works contracts through Directive 71/305/EEC: transparency, equal treatment and the opening-up of markets. Such rules inevitably entail paperwork: proper publication of notices, evaluation, documentation and reviewability—and this later also encourages the expansion of checking bodies and “second pairs of eyes”. ↩︎
- Federal Republic of Germany: Ordinance of 17 September 1976 on fees for services provided by architects and engineers (Fee Schedule for Architects and Engineers – HOAI), BGBl. I, p. 2805. Available online at: https://dejure.org/BGBl/1976/ (last access: 06.01.2026). ↩︎
- The economic context changes. With the oil-price shock from October 1973, energy prices and inflation rise sharply; cost and schedule risks suddenly become politically and fiscally sensitive. Public-sector clients typically respond not with “courage”, but with tighter controls, more documentary evidence and stronger safeguards, because they are less willing to forgive mistakes amid volatility.
See:
Borowsky, Peter: Turnaround in the early 1970s. In: Bundeszentrale für politische Bildung (bpb): Informationen zur politischen Bildung, No. 258 “Zeiten des Wandels” (Times of Change), 05.04.2002. Available online at: https://www.bpb.de/ (last access: 07.01.2026).
Nagel, Joachim: Monetary policy in times of geopolitical crises and high inflation. Speech at the European School of Management and Technology (ESMT), Berlin, 30.08.2022. Deutsche Bundesbank. Available online at: https://www.bundesbank.de/ (last access: 04.01.2026). ↩︎ - The emergence of new roles “out of thin air” is also historically documented: project control has established itself as a distinct service discipline in large-scale public construction since the 1970s—precisely in response to complexity, pressure on schedules and costs, and the division of labour. Since the services listed by way of example in § 31 HOAI 1996/2002 did not meet either clients’ or contractors’ requirements for a defined scope of project-control services, the AHO specialist commission “Projektsteuerung/Projektmanagement” first drew up such a service specification in 1996. It has been continuously developed from that initial approach.
See footnote 1. ↩︎ - In the anonymised case discussed here, a separate interest invoice for around EUR 7,100 was submitted towards the end of the project. It concerned not an isolated case but all the contractor’s interim/part-payment invoices: 41 items over several years. What stood out was less the amount claimed than the ability to assert periods of late payment across the entire series of invoices. Internal checks revealed discrepancies even in the fundamentals: the basis for determining when payment fell due and default arose under VOB/B (including different approaches under § 16(1), no. 3, and § 16(5), no. 3, sentence 3), the relevant date (invoice date versus receipt of the invoice), and the calculation basis (amount invoiced versus amount approved after checking). The claim was subsequently reduced substantially—to roughly one seventh—partly by invoking objections such as the limitation of claims for older years (§§ 195 and 199 BGB) and the late, retrospective assertion of interest. Whatever the outcome of the individual case, the process illustrates the additional work and checks generated by delayed payments themselves: calculating interest, counter-checking, checking the legal position and correspondence. ↩︎
- The fact that the interest claim ultimately amounts to only a low four-figure sum does not refute the thesis, but shifts the focus: the decisive finding is the reproducibility of late payment across a long series of invoices—and the checking work it generates. In other words, the symptom is not the amount of interest, but the fact that the system allows widespread late payment to pass as a plausible account of events at all. ↩︎
- Things were not automatically better in the past, but often simply riskier and technically simpler, with lower demands on energy, accessibility, fire protection, hygiene, acoustics, documentation and warranty – many of today’s rules have emerged from actual cases of damage and deliberate policy objectives for quality. ↩︎
- Rather than terminating the contract, the client commissioned no further stages of services; an assessment of partial services was intended to draw a surgically precise boundary through the unfinished service phases—across the building complexes, across the subprojects and across the service phases. That was the original plan. ↩︎
- The situation described is typical of major public-sector projects involving existing buildings. When the available design is judged inadequate and threatens to bring construction to a halt, time pressure arises that makes regular procurement procedures practically impossible. The result is often a direct award or a tightly constrained negotiated procedure under the guiding principle of “keeping construction moving”. At the same time, public authorities remain bound by their checking and documentation procedures: proposals must be made suitable for checking, the scope of services clarified, supporting documents supplied, additional services justified, and proposed staffing and working hours shown to be plausible and secured in legal and budgetary terms. This succession of safeguards creates a second timeline, out of step with the technical needs of the construction site. For the commissioned architectural practice, this is financially precarious: it must retain project staff for design checks, design coordination, consultation with specialist designers, preparation of procurement documents, scheduling and interface coordination, although the contractual basis—and thus the ability to invoice—is only gradually settled. In practice, internal reserves and liquidity are tied up, not because architecture is “more expensive”, but because commissioning, documentation and payment form a separate cycle of work. The resulting reminders and late-payment interest are less incidental than a consequence of the arrangement: delays in commissioning and payment generate further correspondence, counter-checks and legal assessments—more administrative work only indirectly related to progress on site. ↩︎
- Individual errors of judgement attract visible sanctions—audits, objections and demands for repayment—while courageous, pragmatic decisions are rarely rewarded. This is a problem of incentives. ↩︎
- Here we should refer back to the first part of the series, Guilt and Evidence: in a vivid example, a tradesperson who “drives a nail into the wall” must pass through up to nine stations before that nail is recorded as work paid for (site management → the company’s accounts department → site supervision → project control → public-sector client → its controlling department → possibly the funding body and the Court of Auditors, etc.). This bureaucratic idling ties up working capacity and liquidity: small firms cannot afford to wait months for payment and may, at worst, leave the site, causing further delays.
See Yakubovich, Daniel: A Paper Trail into the Earth, Guilt and Evidence – Part I, synagogen.org, online: https://pensarium.de/ (Version: January 2026). ↩︎ - Chamber of Architects Berlin: Requirements and procedure – registration in the register of architects and urban planners, online: https://www.ak-berlin.de/ (last access 11.01.2026). ↩︎
- VOB/B § 16: Payment. In: Procurement and Contract Regulations for Construction Works – Part B (VOB/B), dejure.org, available online at: https://dejure.org/gesetze/VOB-B/ (last access: 11.01.2026). ↩︎
- “The purchase cost of each ambulance is around EUR 260,000.”
See Wilczek, Markus: Two new ambulances for more than 500,000 euros, come-on.de, online: https://www.come-on.de/ (last access: 28.01.2026) ↩︎ - Several bodies often check the same things: external reviewers and authorities check designs; experts and building-control authorities review safety concepts. For example, site supervision (the architect) could check invoices; having project control check those checks is unnecessary if site supervisors can check properly. ↩︎
- Based on the sources below, approximately 1.5–3.0 per cent of construction costs can be taken as a rough guide to project-control fees: on EUR 60 million, approximately EUR 0.9–1.8 million. The AHO defines a distinct scope of services for delegable client tasks and derives fee recommendations from it. Dispensing with separate project-control services by strengthening the expertise of public construction departments—combined with a radical reduction in formal requirements—would remove the additional cost of commissioning a separate project controller and creating further interfaces. Multiple checks also typically generate costs for second opinions and coordination, particularly in structural stability and fire protection. If checking engineers perform statutory building-control checks and redundant rechecking is thereby eliminated, an additional saving in the low six figures is plausible.
Unternehmen OWL: Clients increasingly commissioned project controllers, 26.10.2020. Available online: https://www.unternehmen-owl.de/ (last access: 11.01.2026).
compa: Project management at construction: Overview of tasks (AHO), 20.11.2025. Available online: https://www.compa.co/ (last access: 11.01.2026). ↩︎ - Audits by the Court of Auditors, compliance and value for money, internal-control requirements – all this creates a climate in which the “safe file” is valued more highly than a prompt decision. In Berlin, the Court of Auditors’ remit and the basic principles of scrutiny are explicitly laid down.
https://www.berlin.de/sen/finanzen/ ↩︎ - In Berlin, there are Integrated project management and multi-party contracts already – so far visible especially in the federal building, for example in the new BAM GBD 149 building in Berlin-Adlershof, which is explicitly “implemented using integrated project delivery (German abbreviation: IPA)” and organized through a multi-party contract. https://bundesbau.de/ ↩︎
- This becomes apparent in building design: the sums often rise not linearly, but through substantial upward revisions following reassessments—in this example, from EUR 588,630.40 to EUR 915,546.79, an increase of 56 per cent. Ancillary construction costs thus become the real arena of systemic friction. ↩︎
- Financial Administration of the State of North Rhine-Westphalia: Advance VAT returns. Tax information – companies – VAT. Available online at: https://www.finanzamt.nrw.de/ (last access: 11.01.2026). ↩︎